South Korea Weighs KF-21 Block 2 Production Delay Amid Rising Costs

Seoul—South Korea’s Defense Acquisition Program Administration is considering delaying completion of Korea Aerospace Industries’ KF-21 Block 2 mass production by more than two years as costs continue to rise.

Under the original plan, 40 KF-21 Block 1 fighters were to be produced by 2028, followed by 80 Block 2 aircraft by 2032.

The revised timeline affects the Block 2 program. According to a report by the Korea Institute for Defense Analyses, South Korea’s Defense Acquisition Program Administration (DAPA) estimated in August 2024 that acquiring 80 Block 2 aircraft would cost KRW14.2 trillion ($10.7 billion at the time). By March 2026, the projected cost had increased to KRW18.4 trillion.

The weakening South Korean won is a major driver of the increase. The exchange rate increased approximately 18% between August 2024 and March 2026, and around 35% of the KF-21’s value consists of imported components, including the General Electric F414-GE-400K engine.

 

DAPA also cited inflation and supply chain instability as contributing factors behind the higher costs.

According to Yonhap News Agency, DAPA is considering stretching production of the 80 Block 2 aircraft from the current 2028-32 timeline to 2034 or 2035. Under such a plan, Korea Aerospace Industries would reduce annual production from around 20 aircraft to approximately 15 aircraft per year for the Republic of Korea Air Force.

Multiple industry sources told Aviation Week that securing export orders during the early Block 2 production phase will be critical in mitigating the impact of a delay and expressed concern that failure to export at least 20 KF-21 Block 2 aircraft beyond 2028 could further increase unit costs and weaken economies of scale for the program.